CES, as Lead Designer, along with Ric-Man Construction FL as Lead Design/Builder, were selected by the City of Miami Beach to provide Design/Build services for West Avenue Improvements Phase II North of 14th Street, as well as West Avenue Improvements Phase II South of 14th Street. These projects are integral in the CIty's ongoing resiliency improvements to address sea level rise. 

The project scope Includes: water main, gravity sewer and stormwater system improvements, including a new 60,000 GPM pump station. The projects also include roadway reconstruction, including raising West Avenue and adjacent streets to minimum crown elevation of 3.7 feet (NAVD), harmonizing raised roadway with adjacent properties and streetscape improvements, throughout the West Avenue corridor. 