Building 3095 Office Building & Hangar Renovation
Part of the expansion and improvements at Miami-Dade International Airport required the complete overhaul and renovation of Building 3095. The building served both as office space and hangar for American Airlines Miami operations. Primary responsibilities for the construction engineering & inspection services consisted of:
- Coordination and technical inspection of the work until final completion and acceptance by the client
- Verification of materials furnished and work performed to ensure compliance with County requirements
- Verification that work progressed on schedule
- Identified and recommended solutions to potential problems
- Ensured threshold inspections were carried out and within code requirements
- Taking necessary actions to prevent the installation of materials or equipment found not to comply with contract documents
- Performing final inspection and making recommendation of acceptable to AA/MDAD